Winscales Moor Wind Farm
Owned by: , tel: +44 20 7042 9600
the Carlisle to Barrow Railway Journey Windspot Leaflet featuring Winscales Moor
13/05/09 Wind Farm operational and ahead of schedule
The wind farm at Winscales started officially operating today, although some turbines have been turning as early on as 2 April due to works being completed ahead of schedule.
01/02/09 A second project receives grant from Wind Farm fund
The Great Clifton Village Hall has received £5,200 towards a new central heating system, to replace the inefficient electric bar heating system currently in use. Eva, Chairperson for the Village Hall Committee said "the heating has made a big difference, the hall was only being used 2 or 3 times a week. Recently we have had 11 bookings for one week, including three for one day".

10/11/08 First local project benefits from Community Fund
An energy-efficient renovation project at the well-used Little Clifton Village Hall has become the first local scheme to benefit from the Community Fund. The fund has contributed more than £8,000 towards the popular hall's vital revamp. With the wind due to begin generating renewable electricity in Spring 2009, we look forward to the Community Fund being used to benefit more local projects.
16/06/08 Construction work now underway
We are delighted to announce that construction work has started on the 7-turbine wind farm. We have engaged Cumbrian firm Story Construction as our contractor and expect the wind farm to begin generating safe, clean, renewable electricity in 2009.
25/01/08 Community Fund
We want the community to benefit from the wind farm as soon as possible, and are pleased to have signed an agreement with the Cumbria Community Foundation to work closely with the parishes of Winscales, Great Clifton and Little Clifton to administer community funds from the wind farm.
20/06/07 Wind Farm Approval!
We are delighted that the Allerdale Borough Council voted in favour of the project! All going to schedule, the wind farm will be operational by the end of 2008.
04/05/07 Decision scheduled soon
The Allerdale Borough Council have indicated that they will be deciding the application for a 7 turbine wind farm at Winscales at their Planning Committee meeting on 7 June 2007.
26/02/06 Newsletter sent to over 6,000 residents
Residents within a 4km radius of the project site will receive a newsletter in their letterbox this week, giving more information about the proposal and enabling them to get in touch with any questions or comments.
with your questions or comments, or subscribe to our mailing list (see the link at the bottom of this page) to ensure you are kept up to date with the latest project information.
11/12/06 Winscales Moor - application submitted
An application for a 7 turbine wind farm near Workington has been submitted to the Allerdale Borough Council.
29/09/06 Winscales Moor Wind Farm
A project to build a 7 turbine scheme adjacent to an existing wind farm in Cumbria has been announced.
|